History
The potential of the Nam Theun River on the Nakai Plateau for hydroelectric power was identified as early as 1927, but it was not until the mid-1970s that detailed studies of the feasibility of a project began. In the late 1980s the Lao government targeted Nam Theun 2 as a key vehicle for the economic and social development of the nation, and invited the World Bank to participate in the Project. The government and various private investors set up the Nam Theun 2 Electricity Consortium (NTEC) to research and develop the scheme. In 1994 Electricité de France and the Italian-Thai Development Company of Thailand joined the Project, and Nam Theun 2 moved from a conceptual to a development phase. The design and preparation of a complete set of economic, environmental and social safeguards took more than ten years, during which time NTEC became the Nam Theun 2 Power Company, or NTPC. Project financing was gradually put in place and full construction activities commenced in June 2005.


Milestones

1927 Nam Theun River’s hydropower potential described in L"Eveil Economique de l'Indochine
1989-91 World Bank feasibility study undertaken by Snowy Mountains Engineering Corp.
1993 GoL and NTEC sign Project development agreement in accordance with World Bank guidelines
1997 First series of environmental and social safeguards documents produced
1997-98 Asian Financial Crisis: Governments of Lao PDR and Thailand agree to delay Project
May 2000 EGAT and NTEC agree on a proposed electricity tariff in May
September 2001 Shareholders Agreement signed
September 2002 NTEC and Lao Government create NTPC as a Lao company
October 2002 Concession Agreement signed
November 2003 Power Purchase Agreements signed with both EGAT and EDL
2004 Completion of safeguard documents and Project financing activities
May 2005 Financial Closure (FC) and beginning of full construction activities
November 2005 Nam Theun 2 Cornerstone Ceremony
2005 Construction activities commence and implementation of safeguards
April 2006-April 2008 Construction of resettlement villages and relocation of villagers to new homes
March 2008 Concreting of the diversion tunnel completed
April 2008 Diversion tunnel closed and impoundment begins
June 2008 Tunnel filling test
August 2008 Spillway gates closed on Nakai Dam
October 2008 First filling of hydraulic circuit; Third Stakeholder Forum in Thakhek
January 2009 Water releases from Nakai Dam for testing and commissioning
March 2009 Regulating Dam impoundment commences; energisation of 500 kV Transmission Lines & Substation
June 2009 Successful testing of first Francis Unit turbine and synchronisation with Thai national grid

 
 
Upcoming Events
July 2010

  • Regional Environmental & Social Management training visits
  • MRC 3rd Regional Stakeholder Forum

September 2010

  • Hydro 2010 International Conference, Lisbon
November 2010
  • 450th Anniversary of Vientiane as Lao capital
December 2010
  • Nam Theun 2 Official Opening Ceremony
 
Link to Javascript Menu Source